Case study · Cladding remediation · QCI · Glasgow

Cladding remediation, checked at every stage.

McKay Turner Consulting acted as the client's independent façade inspector on the cladding remediation of Bridge House in Glasgow, reviewing the remediation design information and monitoring the works on site from strip-out to scaffold strike.

Bridge HouseGlasgow2026
Bridge House, Glasgow, a multi-storey student residential building with grey fibre cement rainscreen and buff brickwork, partly scaffolded during façade remediation works
9
site inspections
6 months
of works monitored
2–3 wks
between site visits
2
façade systems inspected
1
Stage 5 design pack reviewed
100%
of actions assigned an owner

The building

A riverside building, re-clad

Bridge House is a multi-storey student residential building close to the River Clyde in Glasgow, clad in a mix of fibre cement rainscreen panels and brickwork over a framed backing wall, with curtain walling at ground floor and to the stair cores.

The remediation works involved stripping the existing rainscreen and areas of brickwork, then rebuilding the external wall with a new build-up of insulation, membranes, fire-rated cavity barriers and rainscreen panels, delivered by a main contractor and a specialist façade subcontractor.

The brief

An independent eye on the client's behalf

The client wanted independent assurance that the remediation was being designed in enough detail and built in line with it, with the products' tested installation requirements met on every elevation.

We were appointed to review the remediation design information for completeness and coordination, and to carry out regular quality control inspections (QCIs) throughout the works, reporting directly to the client and the wider project team.

How we did it

Design first, then eyes on every elevation

At the first visit we reviewed the employer's requirements and set out what the specialist subcontractor's Stage 5 construction pack needed to contain, from interface details and fixings to calculations and installation guides, so the works could be checked against an agreed design.

From June to November we inspected the works from the scaffold every two to three weeks, checking cavity barriers, insulation, membranes, fixings and interfaces against the manufacturers' tested data. Every visit produced a photographic report with each action assigned to the responsible party, and we reviewed the contractor's close-out responses.

Step 1

Design review

Employer's requirements and Stage 5 pack checked for completeness.

Step 2

Site inspections

Nine QCIs from strip-out to scaffold strike.

Step 3

Reporting

Photographic reports with owned, tracked actions.

Step 4

Close-out

Contractor responses reviewed and items closed.

What we checked

The details that make remediation work

Each inspection focused on the elements that decide whether a remediated wall performs as tested, checked while they were still visible.

Cavity barriersOpen-state and vertical barriers, gaps and taping
InsulationMineral wool fit, coverage and fixing
RainscreenPanel fixings, fixed and movement points
InterfacesWindows, curtain walling, copings and soffits
A hand holding two rivets with green and red collars in front of a grey fibre cement rainscreen panel
Checking fixed and movement-point rivets on the rainscreen panels.
A tape measure recording the clearance between an open-state cavity barrier and the back of a rainscreen panel
Measuring the open-state cavity barrier clearance against tested data.

The outcome

Issues closed out while the scaffold was still up.

By the ninth inspection the rainscreen installation was complete and the brickwork was nearing completion. The contractor had issued a close-out report responding to every previous action, and we were satisfied with the actions taken.

With each item raised, owned and resolved during the works, the client goes into handover with a clear photographic record of how the walls were built and checked.

Find it while you can still see it, fix it before the scaffold comes down.

Work with us

Remediation under way? Get an independent eye on site.

McKay Turner Consulting provides remediation design reviews, quality control inspections, FRAEWs and full remediation project management for building owners and contractors across the UK.

© McKay Turner Consulting LtdRemediation design review · Quality control inspections