Case study · Stage 5 façade design · Liverpool

From design gaps to a buildable Stage 5 package.

McKay Turner Consulting reviewed the Stage 5 design information for the cladding remediation of Herculaneum, a high-rise residential building on Liverpool's waterfront, then produced the coordinated Stage 5 façade drawings for the specialist contractor delivering the works.

HerculaneumLiverpool2026
Herculaneum, Liverpool: a glazed high-rise residential tower with stepped balconies rising above a brick and glass ground-floor podium
51
drawings issued
3
drawing issues, Oct–Nov 2026
4
façade systems detailed
19
product systems coordinated
3
site visits to measure and verify
2
phases: review, then design

The building

High-rise living on the Mersey

Herculaneum is a high-rise residential building on the southernmost dock of Liverpool's historic port, with long views up and down the River Mersey.

Its cladding is being remediated: the specialist contractor is replacing the façade cladding and balconies, with aluminium rainscreen cladding, external wall insulation (EWI) render, rendered soffits and fire-rated steel-framed walls all forming part of the new external envelope.

The brief

Is the design ready to build?

With works already under way, the contractor asked us to review the design information produced so far and establish whether it met what a Stage 5 construction pack needs to contain: drawings, specifications, product data, testing, installation guides and calculations.

The review showed that more coordinated construction information was needed. The contractor then appointed us to produce the Stage 5 façade drawings directly, as part of its own team.

How we did it

Review, measure, then draw

We set out a schedule of every drawing and product the Stage 5 pack required, then visited site to measure and record the existing construction, bracketry and interfaces, because existing records were limited.

From the architect's Stage 4 design and specification, we produced the coordinated package: general arrangement plans and elevations, panel and framing setting-out, cavity barrier setting-out, and plan and section interface details. Manufacturers' data was built into the drawings, with a drawing register and change control kept throughout. Design responsibility stays with the contractor's design team; our role is to produce and coordinate the information.

Step 1

Stage 5 review

Existing design information checked against what a Stage 5 pack needs.

Step 2

Site survey

Existing construction, brackets and interfaces measured on site.

Step 3

Drawing production

Plans, elevations, setting-out and interface details drawn.

Step 4

Issue & control

Three drawing issues, with register and change control.

What the package covers

Four façade systems, one coordinated pack

The Stage 5 package covers every façade element outboard of the plasterboard, including penetrations, across the variations found around the building.

Aluminium rainscreenPanel, framing and bracket setting-out
EWI renderRender system setting-out by balcony type
Rendered soffitsSoffit build-ups and interfaces
Fire-rated SFSSteel-framed walls and cavity barrier layouts
A tape measure recording the depth from the rainscreen rail to the face of the insulation, with brackets fixed behind
Measuring existing bracket and cavity depths on site.
Aluminium rainscreen rails and brackets over mineral wool insulation at the base of the façade
Recording the rainscreen support system and insulation.

The outcome

A coordinated package the site can build from.

Between October and November 2026 we issued 51 Stage 5 drawings across three issues, from rainscreen plans and elevations to framing and cavity barrier setting-out and interface details.

The contractor now has one coordinated set of construction information bringing together the architect's design, manufacturers' data and site findings, ready for consultant review, procurement and installation.

Not just comments: the drawings themselves, coordinated and buildable.

Work with us

Remediation design not ready to build? We can help close the gap.

McKay Turner Consulting provides Stage 5 design reviews, façade drawing production, compliance statements and quality control inspections for contractors and building owners across the UK.

© McKay Turner Consulting LtdStage 5 façade design · Cladding remediation