A Bill now before Parliament would make it a legal duty to assess the external walls of every residential building over 11 metres. Here is what it says, who it applies to, and how to prepare.

MTC GuideBuilding owners & managing agentsUpdated November 2026

In short: the Building Safety (Remediation of Unsafe Cladding etc) Bill was introduced on 14 October 2026. If it becomes law as drafted, whoever is responsible for repairing a residential building over 11 m or five storeys must obtain a fire risk assessment of its external walls, fix any unsafe cladding, and publish a plan. Not assessing would be a criminal offence. A competent FRAEW carried out since 16 May 2022 is expected to count.

Status: this is a Bill, not yet law. The details below are as introduced and may change. Royal Assent is expected in the first half of 2027. We will update this guide as it progresses.

Which buildings are in scope

  • Residential buildings in England with two or more dwellings.
  • Over 11 metres high, or with five or more storeys.
  • Completed before 28 June 2022.
  • Privately owned and social housing alike.

Height matters at the margin. If a building is close to 11 m, it is worth having it measured properly before deciding it is out of scope.

What the Bill would require

DutyWhat it means
AssessObtain a fire risk assessment of the external walls from a suitable professional. Regulations are expected to require this to follow PAS 9980, which means a FRAEW.
Make safePut interim measures in place where needed, and remediate unsafe cladding as soon as reasonably practicable.
PlanPrepare a remediation plan, publish it, and share it with residents and leaseholders.
RegisterBuildings of 11 to 18 m (five or six storeys) would go on a new register, alongside the existing register of higher-risk buildings.

The expected timetable

WhenWhat happens
First half of 2027Royal Assent expected
About 2 months laterThe main duties take effect
8 to 10 months after Royal AssentThe register of 11 to 18 m buildings is expected to open
12 months after Royal AssentAssessments due; enforcement for failing to assess
15 months after Royal AssentRemediation plan due

The government's wider target is for every residential building over 11 m with unsafe cladding to be remediated, or to have a date for completion, by the end of 2029.

Does our existing FRAEW count?

As drafted, an assessment made on or after 16 May 2022 does not need repeating if it met the requirements in force at the time. A FRAEW competently produced to PAS 9980:2022 should therefore stand. Appraisals that relied on assumptions, without confirming what is in the wall, are the ones most likely to need more work. The government's 18 quality checks are a good test.

Who is responsible

The duty falls on the "responsible entity": broadly, whoever holds the repairing obligation for the external walls. That can be a freeholder, a head lessee, a housing association, a council, or a resident management or right-to-manage company. Buildings being remediated by their original developer under the developer remediation contract are treated separately.

Penalties

  • Failing to obtain an assessment without reasonable excuse would be a criminal offence.
  • Failing to remediate could lead to up to two years in prison, or a financial penalty of up to £500,000.

What to do now

  1. List your buildings with their height, storeys and completion date.
  2. Mark the ones in scope: over 11 m or five storeys, completed before 28 June 2022.
  3. Gather what you hold: fire risk assessments, FRAEWs, EWS1 forms, drawings.
  4. Check which assessments will count, and which buildings have none.
  5. Programme the rest before the deadline, while assessors have capacity.

Responsible for several buildings? We can review the whole list and give you a register showing what is in scope, what already counts and what is needed. See portfolio FRAEW programmes.

Frequently asked questions

Is the Remediation Bill law yet?

No. It was introduced to Parliament on 14 October 2026 and has to pass both Houses. Royal Assent is expected in the first half of 2027.

Does it apply to buildings under 11 metres?

Not unless the building has five or more storeys. A building under 11 m may still need a FRAEW for other reasons; see Do I need a FRAEW?

Does it apply in Scotland, Wales or Northern Ireland?

The duties described here apply to buildings in England. Scotland and Wales have their own regimes.

Should we wait until it becomes law?

The duty to cover external walls in the fire risk assessment already exists. Starting now also avoids the rush for assessors once the twelve-month clock starts.

Sources and guidance

This guide is a summary for building owners. It is not legal advice.

Related reading

Talk to us

Want to know where your buildings stand?

Send us the list. We reply within one working day.

© McKay Turner Consulting LtdThe Remediation Bill